Skip to content

Some online services unavailable on Saturday 23 November and Monday 25 November

Due to essential maintenance some of our online services will be unavailable over the next few days.

  • On Saturday 23 November between 9am–5pm you will be unable to view your council tax, council tax support and housing benefits accounts or documents while we upgrade our systems.
  • On Monday 25 November between 6–11pm our online parking services will be unavailable. During this time, you won’t be able to review or pay for parking tickets or buy parking permits or visitor vouchers.

We are sorry for any inconvenience while we carry out these necessary works.

Door icon

Completed schemes

Completed schemes

143 Seven Sisters road

Scheme Name: 143 Seven Sisters Road

Site Address: 143 Seven Sisters Road, N7

Start Date: November 2010

Completion Date: March 2013

Scheme Description: Redevelopment of the former doctor's surgery on the corner of Seven Sisters Road and Durham Road

Total Number of units:

Unit Splits: 

  • Social rent: 6

Unit Mix: 

  • 3 x 2 Bed units
  • 1 x 3 Bed units
  • 2 x 5 Bed units

Armour Close

Scheme Name: Armour Close

Site Address: Armour Close, N7

Start Date: August 2008

Completion Date: October 2009

Scheme Description: Former garage site at Armour Close off Roman Way developed to provide 4 award winning 3 bedroom houses

Total Number of units: 4

Unit Splits: 

  • Social rent: 4

Unit Mix: 

  • 4 x 3 Bed units

Belfont Sites 1 and 2

Scheme Name: Belfont Sites 1 and 2

Site Address: Belfont Walk, Williamson Street Estate, N7

Start Date: October 2011

Completion Date: August 2012

Scheme Description: Infill site delivering 2 two-bedroom houses

Total Number of units: 2

Unit Splits: Social rent: 2

Unit Mix: 2 x two-bed units

Belfont Walk

Name: Belfont Walk site 3

Address: Williamson Street Estate (area between 28/29 and46 Belfont Walk), Williamson Street, N7

Start date: April 2019

Completion date: September 2021

Description: Two new homes have been built on an underused piece of land

Total number of homes: Two two-bed homes, for up to 8 people, for social rent

Bennett Court

Scheme Name: Bennett Court

Site Address: Site adjacent to 3 Axminster Road, (Bennett Court Car Park) N7

Start Date: March 2015

Completion Date: June 2016

Scheme Description: Site adjacent to 3 Axminster Road providing 2 new homes

Total Number of units: 2

Unit splits: social rent: 2

Unit mix: 

  • 1 x 2 Bed units
  • 1 x 4 Bed units

Blenheim Court

Scheme Name: Blenheim Court

Site Address: Land adjacent to 59 to 70 Blenheim Court Estate, Cornwallis Road, N19

Start Date: January 2016

Completion Date: August 2017

Scheme Description: Demolition of existing garages/stores and construction of a three storey residential block comprising maisonettes and flats

Total Number of units: 4

Unit Splits: social rent: 4

Unit Mix: 

  • 2 x 1 Bed units
  • 2 x 2 Bed units

Boleyn Road

Scheme Name: Boleyn Road

Site Address: Boleyn Road, N16

Start Date: August 2008

Completion Date: October 2009

Scheme Description: Former Area Housing Office developed to provide 10 new family homes

Total Number of units: 10

Unit Splits: social rent: 10

Unit Mix: 

  • 4 x 2 Bed units
  • 6 x 4 Bed units

Bramber House

Scheme Name: Bramber House

Site Address: John Barnes Library and land to the rear, 275 Camden Road, N7

Start Date: February 2015

Anticipated Completion Date: January 2018

Scheme Description: Demolition of Bramber House and John Barnes Library to provide 34 new homes and a new library

Total Number of units: 34  

Unit Splits: 

  • Sales units: 8
  • Social rent: 16
  • Shared Ownership: 10

Unit Mix: 

  • 20 x 1 Bed units
  • 9 x 2 Bed units
  • 3 x 3 Bed units
  • 2 x 4 Bed units

Brunswick Estate

Scheme Name: Brunswick Estate

Site Address: Brunswick Close Estate, Tompion Street, EC1V

Start Date: June 2014

Completion Date: June 2016

Scheme Description: Demolition of existing garages, oil tank building and 10 bedsit units to provide 13 new homes and landscaping improvements

Total Number of units: 13

Unit Splits: 

  • Sales units: 3
  • Social rent: 6
  • Shared ownership: 4

Unit Mix: 

  • 8 x 1 Bed units
  • 2 x 2 Bed units
  • 3 x 3 Bed units

Camden Estate

Scheme name: Camden Estate

Site address: 1-8 Rowstock Gardens and garages opposite 77-84 Rowstock Gardens, N7

Start date: June 2016

Completion date: June 2018

Scheme description: The proposal is to demolish the bedsits and garages to rebuild 16 flats and three houses respectively and make environmental improvements

Total number of units: 20

Unit splits: social rent: 20

Unit mix: 

  • 2 x 1 Bed units
  • 14 x 2 Bed units
  • 4 x 3 Bed units

Canonbury School House

Scheme name: Canonbury School House

Site address: 122 Canonbury Road, N1

Start date: July 2014

Completion date: July 2015

Scheme description: Former school house redeveloped to provide new housing

Total number of homes: 3

Unit splits: social rent: 3

Unit mix: 

  • 1 x 1 Bed units
  • 2 x 2 Bed units

Centurian Close

Scheme name: Centurion Close

Site address: Centurion Close, N7

Start date: November 2017

Completion date: June 2019

Scheme description: Transformation of a piece of land used for car parking into a block of flats providing homes for 32 people.

Total number of homes: 8 two-bedroom homes for 32 people, all of which are for social rent

Charles Simmons House

Name: Charles Simmons House

Address: Margery Street Estate WC1X

Start date: April 2019

Anticipated completion date: January 2023

Description: Redevelopment of Charles Simmons House and replacement of Margery Street Community centre

Total number of homes: 25 new homes for up to 88 people, all council homes

Size of new homes: 
• 7 x 1 bed homes
• 16 x 2 bed homes
• 2 x 3 bed homes

Commercial unit:
• 1 X Class A1/A3/D1 use

Main contact: Phyllis Mensah-Twumasi 020 7527 7128

Crouch Hall - The Laundry

Name: Crouch Hall - The Laundry

Address: Hanley Crouch Community Centre, Sparsholt Road, N19

Start date: November 2019

Completion date: March 2022

Description: Part of the development programme at Ivy Hall. The laundry has been replaced with 8 four-bed houses

Total number of homes: 8 new four-bedroom homes for 56 people, all for sale.

Docura House Under Croft

Name: Docura House Under Croft, Corker Walk , N7

Start date: November 2009

Completion date: March 2011

Description: Undercroft area of Docura House on the Andover Estate providing 5 new houses

Total number of homes: 5, all council homes

Size of the new homes: 5 x 3 Bed units

Dover Court Estate

Name: Dover Court Estate (Phase 2), N1

Start date: October 2018

Completion date: November 2021

Description: Underused sites on the estate have been redeveloped into homes. There has also been estate-wide improvements including improvements to the Mitchison Baxter Park to provide a much more usable space for the community.

Total number of homes: 27 homes providing accommodation for 112 people, all for social rent

Size of new homes
• 2 x 1 bed homes
• 14 x 2 bed homes
• 11 x 3 bed homes

Elthorne Estate – Mulkern Road

Scheme Name: Elthorne Estate – Mulkern Road

Site Address: Elthorne Estate – Mulkern Road, N19

Start Date: April 2011

Completion Date: December 2013

Scheme Description: Demolition of the single storey garages to provide new homes

Total Number of units: 7

Unit Splits: 

  • Social rent: 7

Unit Mix: 

  • 1 x 3 Bed units
  • 6 x 4 Bed units

Main Contact: Nick Gore, 020 7527 8040

Elthorne Estate – Holland Walk

Scheme Name: Elthorne Estate – Holland Walk

Site Address: Elthorne Estate – 100 Holland Walk, N19

Start Date: April 2011

Completion Date: February 2013

Scheme Description: Demolition of the dog training centre to provide new homes

Total Number of units: 6

Unit Splits: 

  • Social rent: 6

Unit Mix: 

  • 2 x 2 Bed units
  • 4 x 3 Bed units

Main Contact: Nick Gore, 020 7527 8040

Ewe Close (Shearling Way)

Scheme Name: Ewe Close (Shearling Way)

Site Address: Ewe Close Car Park, N7

Start Date: June 2017

Completion Date: March 2019

Scheme Description: Redevelopment of car park into 4 four-bedroom townhouses

Total Number of units: 4

Unit Splits: 

  • All 4 units are for social rent

Unit Mix: 

  • 4 x 4 Bed units

Main Contact: Souad Akbur, 020 7527 6387

Goodinge Community Centre

Scheme Name: Goodinge Community Centre

Site Address: Goodinge Community Centre, 21 North Road, N7

Start Date: April 2016

Completion Date: February 2018

Scheme Description: Demolition of existing single-storey community centre to erect six-storey building comprising a community centre at ground floor and 23 residential units on upper levels

Total Number of units: 23

Unit Splits: 

  • Social rent: 19
  • Shared Ownership: 4

Unit Mix: 

  • 17 x 2 Bed units
  • 6 x 3 Bed units

Main Contact: Rosemarie Jenkins, 020 7527 8808

Graham Street

Scheme Name: Graham Street

Site Address: 99 Graham Street, N1

Start Date: April 2011

Completion Date: March 2012

Scheme Description: New housing on the former garage site located between Jessop Court and Angelis Apartments

Total Number of units: 5

Unit Splits: 

  • Social rent: 5

Unit Mix: 

  • 1 x 2 Bed units
  • 4 x 3 Bed units

Main Contact: Nick Gore, 020 7527 8040

Holly Park Estate and Community Centre

Scheme Name: Holly Park Estate and Community Centre

Site Address: Holly Park Estate, Ivy Hall Community Centre,  N4

Start Date: November 2014

Completion Date: July 2017

Scheme Description: Demolition of the community centres at Ivy Hall a new community centre and 23 new homes

Total Number of units: 23

Unit Splits: 

  • Social rent: 23

Unit Mix: 

  • 11 x 2 Bed units
  • 7 x 1 Bed units
  • 3 x 3 Bed units
  • 1 x 2 bed units
  • 1 x 1 Bed unit

Main Contact: Teresa Santucci, 020 7527 8114

Holbrooke Court

Scheme Name: Holbrooke Court

Site Address: Holbrooke Ct, N7

Start Date: March 2015

Completion Date: July 2013

Scheme Description: Former garage and unused grassed area

Total Number of units: 5

Unit Splits: 

  • Social rent: 5

Unit Mix: 

  • 2 x 2 Bed units
  • 1 x 3 Bed units
  • 2 x 4 Bed units

Main Contact: Stephen Nash, 020 7527 6337

King Henry's Walk

Scheme Name: King Henrys Walk

Site Address: 24 and 26 King Henry's Walk, N1

Start Date: November 2014

Completion Date: May 2016

Scheme Description: Redevelopment of the not-fit-for purpose bungalows at 24 and 26 King Henry's Walk into a townhouse and a wheelchair accessible bungalow.

Total Number of units: 2

Unit Splits: 

  • Social rent: 2

Unit Mix: 

  • 1 x 3 Bed units
  • 1 x 4 Bed units

Main Contact: Phyllis Mensah–Twumasi, 020 7527 8028

King Square Estate (Phase 1)

Scheme Name: King Square Estate (Phase 1)

Site Address: King Square Estate and part of Moreland Primary School, EC1V

Start Date: January 2016

Completion Date: November 2017

Scheme Description: Demolition of the existing row of garages to the north of Rahere House, nine studio units to the south of Turnpike House and the change of use of the west section of the Moreland School site to residential use to facilitate the building of 140 new residential units, a community centre, a nursery and associated landscaping.

Total Number of units: 47

Unit Splits: 

  • Social rent: 47

Unit Mix: 

  • 25 x 1 Bed units
  • 22 x 2 Bed units

Main Contact: Eleni Tsoskounoglou Koroshilov, 020 7527 2789

King Square Estate

Name: King Square Estate (Phase 2)

Address: King Square Estate and part of Moreland Primary School, EC1V

Start date: June 2017

Completion date: January 2022

Description: Demolition of the existing row of garages to the north of Rahere House, nine studio units to the south of Turnpike House and the change of use of the west section of the Moreland School site to residential use to allow the building of the new homes, a community centre, a nursery and landscaping.

Total number of homes: 93 homes for up to 345 people. 51 for social rent and 42 for sale.

Size of new homes: 
• 17 x 1 Bed units
• 64 x 2 Bed units
• 12 x 3 Bed units

Leigh Road

Scheme Name: Leigh Road

Site Address: 47-53 Leigh Road, N5

Start Date: February 2013

Completion Date: October 2014

Scheme Description: Redevelopment of former reception centre to provide a new sheltered housing block

Total Number of units: 13  

Unit Splits: 

  • Social rent: 13

Unit Mix: 

  • 3 x 1 Bed units
  • 2 x 2 Bed units
  • 2 x 3 Bed units

Main Contact: Nick Gore, 020 7527 8040

Lyon Street

Scheme Name: Lyon Street

Site Address: Lyon St, N1

Start Date: July 2013

Completion Date: December 2015

Scheme Description: Former Area Housing Office redeveloped into a four-storey residential block consisting of 20 flats with associated balconies and communal open space for over 55s

Total Number of units: 20

Unit Splits: 

  • Social rent: 20

Unit Mix: 

  • 2 x 1 Bed units
  • 18 x 2 Bed units

Main Contact: Nick Gore, 020 7527 8040

Mary Seacole Nursery, Tollington Way

Scheme Name: Mary Seacole Nursery, Tollington Way

Site Address: Mary Seacole Nursery at 52 Tollington Way, N7

Start Date: August 2016

Completion Date: March 2018

Scheme Description: Redevelopment of existing building to provide residential homes

Total Number of units: 15

Unit Splits: 

  • Sales units: 7
  • Social rent: 8

Unit Mix: 

  • 4 x 1 Bed units
  • 8 x 2 Bed units
  • 3 x 3 Bed units

Main Contact: Rosemarie Jenkins, 020 7527 8808

Morton Road

Scheme Name: Morton Road

Site Address: Morton Road Car Park, N1

Start Date: September 2016

Completion Date: May 2018

Scheme Description: The redevelopment of the car park and the land to the side of 24 Morton Road into 3 houses

Total Number of units: 3

Unit Splits: 

  • Social rent: 3

Unit Mix: 

  • 1 x 1 Bed units
  • 1 x 2 Bed units
  • 1 x 3 Bed units

Main Contact: Phyllis Mensah–Twumasi, 020 7527 8028

Neptune House/Arundel Grove

Scheme Name: Neptune House/Arundel Grove

Site Address: Arundel Grove/King Henry St, N16

Start Date: September 2009

Completion Date: December 2010

Scheme Description: Former garage site next to Neptune House

Total Number of units: 5

Unit Splits: 

  • Social rent: 5

Unit Mix: 

  • 1 x 3 Bed units
  • 4 x 4 Bed units

Main Contact: Alistair Gale, 020 7527 3976

Otley House

Scheme Name: Otley House

Site Address: Otley House, Gillespie Rd, N5

Start Date: April 2011

Completion Date: March 2012

Scheme Description: Undercroft garages site providing 23 new homes

Total Number of units: 23

Unit Splits: 

  • Social rent: 23

Unit Mix: 

  • 2 x 1 Bed units
  • 18 x 2 Bed units
  • 2 x 3 Bed units
  • 1 x 4 Bed units

Main Contact: David Ronan, 020 7527 7579

Parkhurst road

Scheme Name: Parkhurst Road

Site Address: Parkhurst Rd, N7

Start Date: August 2013

Completion Date: November 2015

Scheme Description: Undercroft garages under 1-52 Trefil Walk and Williamson Street Community Centre to provide  a new community centre and new homes

Total Number of units: 18

Unit Splits: 

  • Sales units: 4
  • Social rent: 12
  • Shared Ownership: 2

Unit Mix: 

  • 17 x 2 Bed units
  • 1 x 3 Bed units

Main Contact: Nick Gore, 020 7527 8040

Redbrick Estate

Name: Redbrick Estate

Address: Old Street/Bath Street EC1V

Start date: July 2017

Completion date: January 2022

Description: Demolition of Vibast Community centre, 169-173 Old Street and Health Centre, partial demolition of garages to west of Bath Street. Building new homes, a community centre, two flexible A1/A2 commercial units across three buildings and landscaping improvement works across the estate

Total number of homes: 55 homes for up to 191 people, all of which will be for social rent

Size of new homes: 
• 16 x 1 bed homes
• 31 x 2 bed homes
• 8 x 3 bed homes

Stacey Street

Name: Stacey Street, Isledon Village, N7

Start date: August 2021

Completion date: June 2022

Description: Conversation of existing building into temporary accommodation with 30 self-contained bedsits

Telfer House

Name: Telfer House

Address: 27 Lever Street, EC1V

Start date: September 2020

Completion date: February 2023

Description: Demolition of an existing residential block and construction of a new residential building with 38 homes and improvements to the landscaping.

Total number of homes: 38 new homes for up to 146 people. 26 of the new homes will be for social rent and 12 will be for sale

Size of new homes: 
• 7 x 1 bed homes
• 25 x 2 bed homes
• 6 x 3 bed homes

Main contact: Souad Akbur 020 7527 6387

Thorpdale Road

Scheme Name: Thorpedale Road

Site Address: Garages, Gainsborough House, 116-124 Thorpedale Road, N4

Start Date: March 2015

Completion Date: June 2016

Scheme Description: Demolition of existing garages to provide 2 new homes

Total Number of units: 2

Unit Splits: 

  • Social rent: 2

Unit Mix: 

  • 2 x 2 Bed units

Main Contact: Mathew Carvalho, 020 7527 8796

Vaudeville Court

Scheme Name: Vaudeville Court

Site Address: Vaudeville Court, St Thomas's Rd/Prah Rd, N4

Start Date: December 2011

Completion Date: February 2015

Scheme Description: Demolition of six existing garages and two sub-stations and the redevelopment of the car park sitebetween Prah Road and St. Thomas' Road providing 13 award winning homes and landscaping improvements

Total Number of units: 13

Unit Splits: 

  • Social rent: 13

Unit Mix: 

  • 7 x 2 Bed units
  • 5 x 3 Bed units
  • 1 x 4 Bed units

Main Contact: Alistair Gale, 020 7527 3976

Vulcan Way

Scheme Name: Vulcan Way

Site Address: Vulcan Way, N7

Start Date: January 2012

Completion Date: May 2013

Scheme Description: Redevelopment of undercroft garages and former car park to provide 17 new homes

Total Number of units: 17

Unit Splits: 

  • Sales units: 5
  • Social rent: 7
  • Shared Ownership: 5

Unit Mix: 

  • 15 x 1 Bed units
  • 2 x 4 Bed units

Main Contact: Alistair Gale, 020 7527 3976

Wedmore Estate

Scheme name: Wedmore Estate, N19

Start date: March 2020

Completion date: January 2023

Description: Transformation of land used for car parking into new homes

Total number of homes: 19 new homes for 77 people, all council homes

Size of new homes: 
• 3 x 1 bed homes
• 9 x 2 bed homes
• 7 x 3 bed homes

Was this information helpful?



Data protection: We will handle your personal information in line with the Data Protection Act 1998 and in accordance with the council’s Fair Processing Notice.